Transfer Log — up to Pay App 12

Park Avenue — Facade Glazing Package
Vantage Facade & Glazing Corp  ·  GC: Ironclad Construction Group
Contract sum to date: $5,137,300.00
Transfers recorded: 5 across 3 events
Net effect on contract sum: $0.00
Every transfer moves scheduled Contract Value between line items — never in or out of the contract. Each event nets to zero: what leaves one line arrives on another, and the contract sum is untouched. This log is the complete history, oldest first.
Transfer 1 — during Pay App 803/12/2026 · by Jordan Silva
Line itemDirectionContract Value
00190  9.9 Contingency Allowance
Base Contract · Section 9
From− $12,500.00
00007  2.2.2 Storefront / Production Shop Drawings & PD
Base Contract · Section 2
To+ $12,500.00
Event net$0.00
Transfer 2 — during Pay App 1005/07/2026 · by Jordan Silva
Line itemDirectionContract Value
00190  9.9 Contingency Allowance
Base Contract · Section 9
From− $8,200.00
00121  5.1 Perimeter Sealant & Flashing
Base Contract · Section 5
To+ $8,200.00
Event net$0.00
Transfer 3 — during Pay App 1106/18/2026 · by Jordan Silva
Line itemDirectionContract Value
00034  3.4.2 Louver Fabrication
Base Contract · Section 3
From− $4,750.00
00190  9.9 Contingency Allowance
Base Contract · Section 9
To+ $4,750.00
Event net$0.00
REQpay Lite · Transfer Log · Park Avenue — Facade Glazing Package Generated 07/27/2026 19:41:02 EST